Southern Area Recycled Water Project; Clean Water State Revolving Fund No. C-06-5319-110 and Water Recycling Funding Program No. 3845-030
29 Documents in Project
Summary
SCH Number
2002011116
Lead Agency
Inland Empire Utilities Agency
Document Title
Southern Area Recycled Water Project; Clean Water State Revolving Fund No. C-06-5319-110 and Water Recycling Funding Program No. 3845-030
Document Type
NOD - Notice of Determination
Received
Posted
7/7/2011
Document Description
The Project will deliver treated municipal wastewater for beneficial reuse, offset State Water supplies, and reduce pumping in the Sacramento/San Joaquin Delta. The Project will expand the Agency's regional recycled water distribution system, and allow recycled water irrigation uses. The Project will involve constructing approximately 14,500 linear feet of recycled water distribution pipeline, installing a 5 million gallon recycled water reservoir, and increasing the recycled water pumping capacity from 8.6 million gallons per day (mgd) to 14.4 mgd. The Project will also involve purchasing two million gallons of storage capacity from the City of Chino Hills 930-reservoir.
Contact Information
Name
Lisa Lee
Agency Name
SWRCB Division of Financial Assistance
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Chino Hills
Counties
San Bernardino
Cross Streets
Galloping Hills Rd
Total Acres
~10
Jobs
1800
State Highways
SR 71
Waterways
Little Chino Creek
Township
2S
Range
8W
Section
No
Base
SBB&M
Notice of Determination
Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.