Amendment to Streambed Alteration Agreement No. 1600-2016-0131-R6 for the Garden Air Wash Storm Drain Project
7 Documents in Project
Summary
SCH Number
2002011078
Lead Agency
City of Calimesa
Document Title
Amendment to Streambed Alteration Agreement No. 1600-2016-0131-R6 for the Garden Air Wash Storm Drain Project
Document Type
NOD - Notice of Determination
Received
Posted
11/2/2018
Present Land Use
The majority of the project site is designated RL Residential Low (2-4 dwelling units per gross acre); additionally, a small portion in the southeastern corner of the project site is designated RR (Residential Rural 0-2 dwelling/units per acre).
Document Description
The project is an Amendment to the Streambed Alteration Agreement No. 1600-2016-0131-R6 for the Garden Air Wash Storm Drain project. Since the issuance of the Lake and Streambed Alteration Agreement, California Department of Fish and Wildlfie approved an update to the mitigation proposal from enhancement and long term management of 0.88 acres of mitigation credits to re-establishment and in-perpetuity management and conservation of a total of 0.82 acres of streamved habitat. CDFW also approved the change of project ownership and the Permittee from Highpointe JPR 308, LLC, to Western Pacific Housing, Inc.
Contact Information
Name
Kim Romich
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Location
Cities
Calimesa
Counties
San Bernardino
Cross Streets
Bryant Street and Greentree Circle
Total Acres
319.65
Parcel #
410-260-015, 09-150-024
State Highways
I-10
Waterways
San Timoteo Canyon
Township
2S
Range
1W
Section
18
Other Information
El Casco
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes