River Street Residential Project (the Courtyards)
8 Documents in Project
Summary
SCH Number
2002011061
Lead Agency
City of Fillmore
Document Title
River Street Residential Project (the Courtyards)
Document Type
NOD - Notice of Determination
Received
Posted
6/4/2004
Present Land Use
The site has a General Plan designation and zoning of Medium Density Residential and Open Space.
Document Description
The applicant proposes to alter the streambed to develop "The Townhomes" at the River residential project site, located east of the Highway 23 Bridge and is bounded by River Street to the north, the Santa Clara River to the south, residential and vacant land to the west and vacant land to the east. The proposed project includes the construction of residences, roadways with curb and gutters, bike paths, common use areas landscaping, the associated portion of the Santa Clara River Levee, and a concrete storm drain outlet. The proposed project will result in 1.25 acres of temporary impacts and 4.45 acres of permanent impacts for a total of 5.70 acres of impacts to California Department of Fish and Game jurisdiction. The Project also has an additional 1.2 acres off-site.
Contact Information
Name
Betty Courtney
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Fillmore
Counties
Ventura
Cross Streets
River and Central
Total Acres
.9
Parcel #
053-140-04,410-290-03 410-290-52
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.