Addendum No. 3 to the MND for the City of San Bernardino Municipal Water Department's Water Systm Reliability Schedule of Improvements
Document Type
NOD - Notice of Determination
Received
Posted
9/19/2011
Document Description
In the 2001 Initial Study, the Department envisioned that two 6 million gallon (MG) water storage reservoirs would be constructed at the Ogden site. One 6 MG reservoir was proposed to be constructed during Phase 3 (mid-term) of the Water System Reliability program, and a second 6 MG reservoir was proposed to be constructed during Phase 5, the final stage of the program. As often happens over a long program, most of the proposed infrastructure facilities have been installed as envisioned, but none of the proposed 12 MG of reservoir storage capacity at the Ogden site has been installed. The proposed change in the original approved project consist of replacing the two 6 MG storage reservoir with a single 12 MG circular, pre-stressed, concrete storage reservoir. This Addendum, combined with the original Initial Study, serves as the basis for a second tier environmental review of the Department's decision to replace the proposed two reservoir facility with a single reservoir facility. The location and storage capacity of the site remains the same as originally proposed and the proposed reservoir operations as an integrated part of the Department's water supply system will also remain the same. Based on the revision to the Ogden reservoir site, the Department concluded that a follow-on CEQA environmental document would be required. The focus of this documentation is on any changes in circumstances that may affect or be affected by the proposal to install a single 12 MG storage reservoir at the Ogden site, instead of the original, proposed two reservoirs.

Contact Information

Name
Mr. Greg Gage
Agency Name
City of San Bernardino Municipal Water Department
Contact Types
Lead/Public Agency

Location

Cities
San Bernardino
Counties
San Bernardino
State Highways
15&215
Railways
Union Pacific/BNSF
Township
1NS
Section
3,4W
Base
SBM

Notice of Determination

Approving Agency
City of San Bernardino Municipal Water Department
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.