Addendum No. 3 to the MND for the City of San Bernardino Municipal Water Department's Water Systm Reliability Schedule of Improvements

4 Documents in Project

Summary

SCH Number
2001121140
Lead Agency
San Bernardino Valley Municipal Water District
Document Title
Addendum No. 3 to the MND for the City of San Bernardino Municipal Water Department's Water Systm Reliability Schedule of Improvements
Document Type
NOD - Notice of Determination
Received
Posted
12/7/2004
Document Description
A 42-inch waterline will run from the intersection of California and Baseline Streets, north up California to 19th Street; east on 19th Street to Flores Street to 20th Street; east on 20th Street to Gardena Street; north on Gardena Street to its terminus; thence west in a vacant, privately owned parcel to the 19th Street Treatment Plant. Implementation of this alignment will require City of San Bernardino Municipal Water Department (CSBMWD) to acquire by negotiated purchase or by eminent domain the right of place and maintain the pipeline in the vacant, privately owned parcel. The CSBMWD is also considering an additional pipeline segment. The segment is a connection to the 48-inch San Bernardino Valley Municipal Water District Baseline Feeder located approximately 900 feet west of California Street on the south side of Baseline Street.

Contact Information

Name
Steve Ledbetter
Agency Name
City of San Bernardino Municipal Water Department
Contact Types
Lead/Public Agency

Location

Cities
San Bernardino
Counties
San Bernardino
State Highways
15&215
Railways
Union Pacific/BNSF
Township
1NS
Section
3,4W
Base
SBM

Notice of Determination

Approving Agency
City of San Bernardino Municipal Water Department
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print