Addendum to the Final Mitigated Negative Declaration for the Chico Municipal Airport, Groundwater Remediation Project
3 Documents in Project
Summary
SCH Number
2001102116
Lead Agency
California Department of Toxic Substances Control
(DTSC)
Document Title
Addendum to the Final Mitigated Negative Declaration for the Chico Municipal Airport, Groundwater Remediation Project
Document Type
NOD - Notice of Determination
Received
Posted
3/16/2004
Present Land Use
The Butte County General Plan has zoned the existing Chico Municipal Airport property site for light manufacturing and commercial use. The proposed groundwater remediation activities are consistent with the current land use of the property
Document Description
The Department of Toxic Substances Control (DTSC) has prepared an Explanation of Significant Difference (ESD) pursuant to authorization granted under Section 117(c) of the Comprehensive Environmental Response, Compensation, and Liability Act and 40 Code of Federal Regulations Section 30.435(c)(2)(I). Preparation of the ESD is required because the preferred discharge method for treated water in the Remedial Action Plan (RAP) approved by DTSC in 2002 is not achievable. The Department of Health Services (DHS), the agency that regulates the drinking water supply has rejected the City of Chico's permit application to discharge to California Water Service.
Contact Information
Name
Ed Cargile
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency
Phone
Location
Cities
Chico
Counties
Butte
Cross Streets
Liberator and Boeing
Total Acres
5,700 ft /1,560
Airports
Chico Municipal
Waterways
Sycamore Creek Channel
Other Information
Project Area Is 5,700 ft. by 1,560 ft.
Notice of Determination
Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.