Lower Feather River Fish Counting Weir - Oroville Facilities Relicensing Program (FERC Project No. 2100)

10 Documents in Project

Summary

SCH Number
2001102011
Lead Agency
California Department of Water Resources (DWR)
Document Title
Lower Feather River Fish Counting Weir - Oroville Facilities Relicensing Program (FERC Project No. 2100)
Document Type
NOD - Notice of Determination
Received
Posted
12/10/2009
Present Land Use
Three primary land use designations in the project area include Public Grazing and Open Land, and Timber Mountain land use.
Document Description
DWR is proposing to install a fish counting weir on the Low Flow Channel (LFC) of the Feather River to obtain data on salmon use. Associated facilities would include an access road from an existing levee to the river and a fenced storage area with a storage facility and electrical housing facility. Power lines would be extended from an existing line at Pacific Heights Road to the electrical housing facility. The proposed project is within the scope of the Fish Weir Program that was received and approved Oroville Facilities Program EIR.

Contact Information

Name
Ms. Gail Kuenster
Agency Name
California Department of Water Resources
Contact Types
Lead/Public Agency

Location

Cities
Oroville
Counties
Butte
Zip
95966
Total Acres
41,000
State Highways
70, 162, 99
Railways
Western Pacific
Airports
Oroville Municipal
Waterways
Feather River, Lake Oroville
Township
18-22N
Range
2E-6E

Notice of Determination

Approving Agency
CA DWR
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes