I-80 Widening and Rehabilitation Project, Dan Wilson Creek Bridge

3 Documents in Project

Summary

SCH Number
2001092054
Lead Agency
California Department of Transportation, District 4
Document Title
I-80 Widening and Rehabilitation Project, Dan Wilson Creek Bridge
Document Type
NOD - Notice of Determination
Received
Posted
10/28/2002
Present Land Use
Intensive Agriculture, Business and Industrial Park, and Highway & Regional Commercial zoning. Uses are agriculture and commercial.
Document Description
SAA R3-2002-0812 The proposed project will involve work in Dan Wilson Creek along Highway 80 in Fairfield, Solano County. Dan Wilson Creek is intermittent in this area and some water may be present during construction. The proposed work will widen both existing bridges of Highway 80 over Dan Wilson Creek resulting in the closure of the gap between the bridges. If flow is present in the creek during the construction period, temporary water diversion systems will be constructed consisting of coffer dams and culverts to bypass flow. In-creek work will consist of excavation for footings, drilling for new pilings, pile driving, forming and shoring of new columns to support the widened bridge structure. To accommodate this work all existing vegetation between the two bridges will be removed and the stream bed will be reshaped. The equipment that will be used to accomplish the work will most likely be bulldozers, backhoes, trucks, earthmovers, cranes, pile drivers, and drilling rigs.

Contact Information

Name
Fred Botti
Agency Name
Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Fairfield
Counties
Solano
Cross Streets
I-680 and I-80

Notice of Determination

Approving Agency
Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print