2nd Avenue/12th Street Roadway Project

3 Documents in Project

Summary

SCH Number
2001081157
Lead Agency
Fort Ord Reuse Authority
Document Title
2nd Avenue/12th Street Roadway Project
Document Type
NOD - Notice of Determination
Received
Posted
5/21/2002
Present Land Use
The site is designated by the Fort Ord Reuse Plan and Fort Ord Infrastructure Master Plan for improvement of the existing 2nd Avenue/12th Street roadway, between 12th Street and Light Fighter Drive and between Highway 1 and Imjin Road, respectively, from two lanes to a four-lane, divided roadway.
Document Description
The project will remove an existing two-lane roadway and construct a four lane divided roadway approximately 2.8 miles long within a 140 foot right of way. The proposed expansion largely follows existing roadways, except for a stretch of road along 12th street. FORA will also construct bicycle lanes and sidewalks, improve drainage facilities, and relocated utility facilities. The project will result in the incidental take of approximately 782 sand gilia plants, a State threatened species, at the Intersection of 12th Street and Imjin Road. FORA will mitigate impacts from the project off-site.

Contact Information

Name
Terry Palmisano
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Marina, Seaside
Counties
Monterey
Cross Streets
2nd Avenue & 12 Street & Light Fighter Drive
State Highways
1(west)
Railways
Southern Pacific Railroad Spur
Airports
Marina Municipal

Notice of Determination

Approving Agency
Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print