Addition to McInnis Park Apartments I - Project File No's ZC00-13 and ED00-146

Summary

SCH Number
2001079026
Lead Agency
City of San Rafael
Document Title
Addition to McInnis Park Apartments I - Project File No's ZC00-13 and ED00-146
Document Type
NOD - Notice of Determination
Received
Posted
7/9/2001
Document Description
The Mitigated Negative Declaration assessed the addition of a new multi-family residential structure with eight studio units to a 5.79-acre site currently developed with 98-multi-family residential units. The approved improvements would entail the construction of a new three-story, multi-family residential structure, composed of nine enclosed parking spaces on the ground level and eight studio apartment units (four units on the first floor and four on the second floor). This new structure would be located immediately west of 85 North Avenue, in an area currently developed with paved parking. The proposal would also include uncovered parking spaces adjacent to the new building, replacement parking spaces throughout the site, and landscaping improvements. The project applications include a Rezoning from the current Planned Development (PD) District to a revised PD District (ZC00-13) and Environmental and Design Review Permit (ED00-146).

Contact Information

Name
Raffi Boloyan
Agency Name
City of San Rafael
Contact Types
Lead/Public Agency

Location

Cities
San Rafael
Counties
Marin

Notice of Determination

Approving Agency
City Council of the City of San Rafael
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.