El Capitan Phase II (8-Lot Residential Subdivision) - Bridge Construction

Summary

SCH Number
2001069038
Lead Agency
City of San Luis Obispo
Document Title
El Capitan Phase II (8-Lot Residential Subdivision) - Bridge Construction
Document Type
NOD - Notice of Determination
Received
Posted
6/8/2001
Document Description
The project consists of constructing concrete abutments, a wooden bridge, and the installation of gabions. The concrete abutments, which are 3 meters by 1.8 meters, will be located outside of the stream bottom. Approximately 5 meters of bank will be disturbed for the abutment and gabions on the right bank. There will be four meters of bank disturbed for an abutment only on the left bank. The gabions will be 4.5 meters in length with a width of one meter. There will be approximately two cubic meters of fill behind the gabions to shape the maintenance access road. The gabion baskets will be hand-set along the bank of the creek and will be planted with willow cuttings to help stabilize the baskets and bank. No equipment will be operated in the creek. The bridge deck is constructed to be above the 100 year high water elevation. The California Department of Fish and Game is Executing a Lake and Streambed Alteration Agreement Number R3-2001-0008 pursuant to Section 1603 of the Fish and Game Code to the project operator, Kelly Gearhart.

Contact Information

Name
Serge Glushkoff
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
San Luis Obispo
Counties
San Luis Obispo

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print