Summary

SCH Number
2001061069
Lead Agency
City of San Diego
Document Title
Strategic Framework Element
Document Type
NOD - Notice of Determination
Received
Posted
10/25/2002
Present Land Use
Citywide General Plan Policy.
Document Description
The recent approvals are to allow the construction of new park amenities and improvements within the Shoreline Parks Master Plan area. The project site is approximately 177 acres, which includes the Bayfront Nature area, Harborview Park, Ryder Park, Seal Point Park, Seal Cove, Bay Marshes, Bayside-Joinville Park and Tidelands Park. The project area is located along the east side the City adjacent to the San Francisco Bay. The project area is zoned S (Shoreline District). A Site Plan and Architectural Review and Site Development Permit were approved for the following: the construction of new public restrooms and shade structures through out the park area; new storage building and entry kiosk at Seal Point Park; new pedestrian and vehicular bridge across San Mateo Creek at Ryder Park; new pedestrian bridge across San Mateo Creek at Rand Street; Seal Slough Bridge railing improvements; new parking lots; grading within the Shoreline Park Master Plan area; and removal of major vegetation.

Contact Information

Name
John Kovac
Agency Name
City of San Diego
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Regions
Citywide
State Highways
84, 56, 54, 125
Airports
Lindbergh/Brown Montgomery
Waterways
San Diego Bay and San Diego River

Notice of Determination

Approving Agency
City of San Diego
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.