Inland Empire Utilities Agency On-Site Dairy Digester / Chino 1 Desalter Power Generation Pilot Scale Project

4 Documents in Project

Summary

SCH Number
2001051132
Lead Agency
Inland Empire Utilities Agency
Document Title
Inland Empire Utilities Agency On-Site Dairy Digester / Chino 1 Desalter Power Generation Pilot Scale Project
Document Type
NOD - Notice of Determination
Received
Posted
7/16/2001
Document Description
The Inland Empire Utilities Agency (IEUA or Agency) is proposing to install, operate and maintain pilot scale digester facilities that are intended to provide a clean, renewable source of methane gas (biogas) as a substitute for natural gas fuel to power back-up power generation facilities (1,750 kilowatts (kW)) that are in the process of being installed at the Chino 1 Desalter. The maximum-sized project that will be considered for approval by the IEUA Board of Directors will produce enough digester biogas to generate 1.75 megawatts (mW) of electricity. This project will be phased, with a first phase digester process estimated to produce enough digester biogas to generate up to 0.5 megawatts of electricity for use at the Chino 1 Desalter or other generators connected to the digester gas distribution system. This digester pilot project is referred to herein as the "Synagro Digester".

Contact Information

Name
Matthew A. Poeske
Agency Name
Inland Empire Utilities Agency
Contact Types
Lead/Public Agency

Location

Cities
Chino
Counties
San Bernardino
Cross Streets
Euclid and Kimball
State Highways
Euclid

Notice of Determination

Approving Agency
Inland Empire Utilities Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print