Blyteh Energy Transmission Line Project

6 Documents in Project

Summary

SCH Number
2001039036
Lead Agency
California Energy Commission
Document Title
Blyteh Energy Transmission Line Project
Document Type
NOD - Notice of Determination
Received
Posted
2/27/2008
Document Description
The Department is issuing a Lake and Streambed Alteration Agreement for the project proponent who proposes to construct approximately 67.4 miles of new transmission line from the Buck Substation in Blythe, west to the Julian Hinds Substation near Hayfield. The route will generally follow Southern California Edison's (SCE) existing 500 kV Devers-Palo Verde ("D-PV1") transmission line. Transmission line structures will be concrete, single-pole structures, spaced approximately every 850 feet along the construction corridor, and will be accessed by spur roads constructed from existing utility access roads. The transmission lines will be constructed using conventional cranes for pole installation. Impacts include building spur roads to access pole installation sites across ephemeral washes. It will also include temporary wash disturbances during pulling, tensioning, and splicing activities, and the installation within washes of some flood-resistant pole structures where no alternative meets maximum span widths. There are approximately 120 unnamed ephemeral or intermittent drainages of the Southern Mojave Watershed and 25 unnamed ephemeral or intermittent drainages of the Southern Mojave Watershed and 25 unnamed ephemeral or intermittent drainage of the Hayfield Dry Lake Watershed. The project proposes to impact approximately 145 of these drainages, for a total cumulative impact of 20.5 acres to jurisdictional streambed.

Contact Information

Name
James Sheridan
Agency Name
California Dept. of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Blythe
Counties
Riverside

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print