Ordnance and Explosive Removal Actions in Sectors 2, 4, and 5 at the Former Benicia Arsenal

2 Documents in Project

Summary

SCH Number
2001032136
Lead Agency
Department of Toxic Substances Control
Document Title
Ordnance and Explosive Removal Actions in Sectors 2, 4, and 5 at the Former Benicia Arsenal
Document Type
NOD - Notice of Determination
Received
Posted
7/11/2001
Present Land Use
Limited Industrial/Open Space
Document Description
The U.S. Army Corps of Engineers will conduct a clearance of ordnance and explosives (OE) in three sectors within the Former Benicia Arsenal as a risk reduction measure. OE that is safe to move will be transported to a controlled demolition area in the Sector and detonated, OE that is unsafe to move will be blown in place. The project has been designed to prevent and buffer any public exposure to intentional and unintentional detonations. The clearance will take 14 weeks and begin in mid-spring.

Contact Information

Name
Donn Diebert
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Benicia
Counties
Solano
Cross Streets
Rose Drive and East Second Street
Zip
94510
Total Acres
135
State Highways
I-680, I-780
Waterways
Sulphur Springs Creek
Township
3N
Range
3W
Section
24

Notice of Determination

Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.