R-6 Reservoir Joint Use Improvement Project

3 Documents in Project

Summary

SCH Number
2001031076
Lead Agency
El Toro Water District
Document Title
R-6 Reservoir Joint Use Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
7/26/2001
Present Land Use
Zoned Recreation/Open Space
Document Description
The R-6 Reservoir, which was constructed in 1967, is a large potable water reservoir owned, operated and maintained by the District within the City of Mission Viejo. The R-6 Reservoir Joint Use Improvement Project (Project) is a regional water supply reliability project being sponsored jointly by the District, Santa Margarita Water District and Moulton Niguel Water District. The benefits of the project include improving emergency water reserves by increasing reservoir storage capacity in south Orange County. The regional nature of the project enhances the availability of stored potable water in an area of critical need to meet existing emergency water reserve demands for each sponsoring agency's respective service area. Other than through the provision of additional emergency storage capacity, the Project is neither designed nor intended to increase operational capacity beyond pre-project levels.

Contact Information

Name
Robert Hill
Agency Name
El Toro Water District
Contact Types
Lead/Public Agency

Location

Cities
Mission Viejo
Counties
Orange
Cross Streets
23392 La Glorieta-Las Flores/Vallejo
Zip
92691
Parcel #
809-461-08
Township
6S
Range
8W
Section
25
Base
SB

Notice of Determination

Approving Agency
Department of Water Resources
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print