Revised Solid Waste Facility Permit (SWFP # 28-AA-0002) for Clover Flat Landfill

2 Documents in Project

Summary

SCH Number
2001022013
Lead Agency
Napa County
Document Title
Revised Solid Waste Facility Permit (SWFP # 28-AA-0002) for Clover Flat Landfill
Document Type
NOD - Notice of Determination
Received
Posted
3/23/2001
Present Land Use
Agriculture, Watershed and Open Space
Document Description
Request for modification of Use Permit #U-438889 to allow an increase of the daily maximum capacity throughput from 300 to 600 tons/day; to allow changes in the location of gas monitoring probes as deemed necessary by future revised Gas Monitoring Plan, approved by the LEA; and to accept de-watered, non-hazardous sludge with less than 50% liquid, revising the condition limiting acceptance from only Calistoga Wastewater Treatment Plant. The landfill is located on 43 acres of a total 112-acre parcel, 2000 feet north of Silverado Trail, approximately 1 mile east of Dunaweal Lane (APN:20-120-17, 18, & 18-050-026) in the AW (Agricultural Watershed) zoning district, and the AWOS (Agriculture, Watershed and Open Space) General Plan Land Use Area.

Contact Information

Name
Erica Weber
Agency Name
California Integrated Waste Management Board
Contact Types
Lead/Public Agency

Location

Cities
Calistoga
Counties
Napa
Cross Streets
Silverado Trail/Dunaweal Lane
Total Acres
112
Parcel #
020-120-017
Township
9N
Range
6W
Section
33
Base
Mt. Diab

Notice of Determination

Approving Agency
California Integrated Waste Management Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A