Montgomery Creek Outfall Project (Lake or Streambed Alteration Agreement No. 1600-2016-0122-R3)

3 Documents in Project

Summary

SCH Number
2001012030
Lead Agency
Santa Rosa, City of (City of Santa Rosa)
Document Title
Montgomery Creek Outfall Project (Lake or Streambed Alteration Agreement No. 1600-2016-0122-R3)
Document Type
NOD - Notice of Determination
Received

Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2016-0122-R3 pursuant to section 1602 of the Fish and Game Code to the project Applicant, Don Boehm, REO Capital Fund 4, LLC, A Limited Liability Co. The project will install a new 15-inch storm drain outfall structure which will serve a new 6 home subdivision at the approx. 1.16 acres site. The project includes the installation of low impact development treatments (LID); the outfall structure will convey high flows not captured by the on-site LID features. The outfall is located at the top of bank approx. 50 feet from Santa Rosa Creek high flow channel. Above the culvert outfall, the bank will be graded to an approx. 2:1 slope and below the culvert the bank will remain at an approx. 1:1 slope. The circumference of the outfall will be armored with approx. 2 to 3 feet of rockslope protection. Native vegetation will be planted below the outfall on the floodplain. The project will impact approx. 23 linear feet of bank. All work will be conducted from the top of the bank.

Contact Information
Lorie Hammerli
CDFW
7329 Silverado Trail
Napa, CA 94558

707-576-2880

Location

Cities
Santa Rosa
Counties
Sonoma
Cross Streets
SR-12, Highway-101
Total Acres
29,100+/-
State Highways
SR-12, Highway-101
Railways
Northwest Pacific
Airports
Sonoma County
Waterways
Santa Rosa Creek/Laguna de Santa Rosa

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
7329 Silverado Trail, Napa, CA 94558

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search