Water System Improvement Project

6 Documents in Project

Summary

SCH Number
2001011027
Lead Agency
Chiriaco Summit County Water District
Document Title
Water System Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
4/5/2001
Document Description
The project consists of construction of a metered turn-out facility on the Colorado River Aqueduct with magnetic flow meter and electrical service, construction of approximately 4,000 linear feet of replacement water transmission and distribution pipelines, construction of a roofed, 300,000-gallon treated water storage reservoir, rehabilitation of an existing 300,000-gallon open raw water storage reservoir, construction of a 40-gpm water treatment and pumping facility, and implementation of a water-exchange agreement between the District, the San Bernardino Valley Municipal Water District, and the Metropolitan Water District of Southern California enabling the District to continue to use surface water from the Colorado River Aqueduct.

Contact Information

Name
Margit F. Chiriaco-Rushe
Agency Name
Chiriaco Summit County Water District
Contact Types
Lead/Public Agency

Location

Counties
Riverside
Cross Streets
I-10: Chiriaco Summit Exit
Zip
92201
Total Acres
2+/-
Parcel #
709-200-002, 003; 709-210-001, 004, 011, 012, 017
State Highways
I-10
Airports
Chiriaco Summit
Township
6S
Range
12E
Section
10
Base
SBM
Other Location Info
Chiriaco Summit

Notice of Determination

Approving Agency
Chiriaco Summit County Water
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print