Sunrise Power Project
8 Documents in Project
Summary
SCH Number
2000129017
Lead Agency
California Energy Commission
Document Title
Sunrise Power Project
Document Type
NOD - Notice of Determination
Received
Posted
12/11/2000
Document Description
The Project involves construction and operations of a 320-megawatt power plant and associated transmission lines, water and natural gas pipelines and an access road. The Project could result in the "take" of the following species protected under the California Endangered Species Act: San Joaquin antelope squirrel, giant kangaroo rat, Tipton kangaroo rat, Bakersfield small scale and California Jewel Flower. The Department will need to issue an Incidental Take Permit for the Project.
Contact Information
Name
Donna Daniels
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
Kern
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes