Evergreen Valley College Facilities Master Plan, October 1999

6 Documents in Project

Summary

SCH Number
2000112004
Lead Agency
San Jose-Evergreen Community College District
Document Title
Evergreen Valley College Facilities Master Plan, October 1999
Document Type
NOD - Notice of Determination
Received
Posted
8/17/2001
Present Land Use
Designation: Pubic/Quasi-Public Zoning: R-1:B-1, R-1:B-2, R-1:B-8, and Agriculture.
Document Description
The proposed Facilities Master Plan involves the expansion of campus facilities and modifications to campus access and circulation. The proposed projects would involve construction of new facilities (approximately 285,000 square feet), renovation of some facilities, expansion of parking lots and possible construction of a parking structure, a new access road from the western end of the campus, and a relocated eastern campus access from Yerba Buena Road. A commercial center at the corner of San Felipe Road and Yerba Buena Road is being developed privately, and has undergone separate environmental review under CEQA. All of the proposed facilities would be developed within the existing campus boundaries. The development proposed under the Facilities Master Plan is intended to meet the needs of the College for an anticipated enrollment of approximately 16,000 total students by the year 2010.

Contact Information

Name
Robert Mibach
Agency Name
San Jose-Evergreen Community College District
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
San Felipe Road, Yerba Buena Road
Total Acres
165.5
Jobs
239
Parcel #
660-21-13, -14, -16, and -19

Notice of Determination

Approving Agency
San Jose-Evergreen Community College District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print