Tahoe Forest Hospital Western Addition Expansion Project

3 Documents in Project

Summary

SCH Number
2000102106
Lead Agency
Tahoe Forest Hospital District
Document Title
Tahoe Forest Hospital Western Addition Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
2/5/2001
Present Land Use
Public Hospital / Office, Zoning: Public Facilities, General Plan: Public Hospital/ Office
Document Description
The Tahoe Forest Hospital Western Addition Expansion project is located at the existing Tahoe Forest Hospital facility at 10121 Pine Avenue. The existing main hospital facility is located on a 7.4 arce L-shaped parcel with Levone Avenue to the east, Spring Lane to the south, Donner Pass Road to the north and Pine Avenue to the west. The portion of Pine Avenue from Tahoe Drive to Spring Lane was abandoned in 1994. The remaining portion of Pine Avenue will lead directly to the proposed new Hospital entrance. The Western Addition expansion and parking improvements will be constructed over the portion of Pine Avenue that has been previously abandoned.

Contact Information

Name
Larry Long
Agency Name
Tahoe Forest Hospital District
Contact Types
Lead/Public Agency

Location

Cities
Truckee
Counties
Nevada
Cross Streets
Donner Pass Road and Pine Avenue
Zip
96160
Total Acres
8.2
Parcel #
18-630-08
State Highways
Interstate 80
Railways
Union Pacific
Airports
Truckee Tahoe
Schools
Tahoe Truckee Unified School District
Waterways
Truckee River
Township
17N
Range
16E
Section
16
Base
MDM

Notice of Determination

Approving Agency
Tahoe Forest Hospital District Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.