Surface Mining Permit No. 202
3 Documents in Project
Summary
SCH Number
2000101063
Lead Agency
Riverside County
Document Title
Surface Mining Permit No. 202
Document Type
NOD - Notice of Determination
Received
Posted
7/11/2002
Present Land Use
Current land uses for the majority of the site Temescal/El Cerrito Community Plan - Mining (M), a 17.1-acre portion is currently designated Specific Plan 176-Planning Area IV - 2 - IP Industrial Park. Current zoning for the majority of the site is M-R-A (Mineral Resources and Related Manufacturing), a 17.7 acre portion is currently zoned SP (Specific Plan)
Document Description
General Plan Amendment changing the land use designation on 17.77 acres to be added to SMP 202 from "Specific Plan 176" to "M (Mining)"; Specific Plan Amendment removing the 17.77 acres from Specific Plan 176; Change of Zone changing the designation of Specific Plan (SP) to Mineral Resources and Related Manufacturing (M-R-A) on the 17.77 acres; and Surface Mining Permit to reauthorize aggregate materials excavation for a 215 acre site, to expand the 121 acre excavation area, to extend permit duration, to recycle inert construction debris, and to revise the reclamation plan to incorporate groundwater recharge.
Contact Information
Name
James Quirk
Agency Name
Riverside County Planning Department
Contact Types
Lead/Public Agency
Phone
Location
Cities
Corona
Counties
Riverside
Cross Streets
Temescal Canyon Road and Maitri Road
Total Acres
215
Jobs
211
Parcel #
290-040-018, 043, 290-060-015, 021, 290-090-015, 290-110-014, 016, 021, 022
State Highways
I-15
Township
5S
Range
6W
Section
2/3/10
Base
SBM
Other Information
Section con. 11
Notice of Determination
Approving Agency
Riverside County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes