East Campus Student Apartments, Phase 2

5 Documents in Project

Summary

SCH Number
2000081006
Lead Agency
University of California, Irvine
Document Title
East Campus Student Apartments, Phase 2
Document Type
NOD - Notice of Determination
Received
Posted
3/15/2002
Present Land Use
The UCI Long Range Development PLan, as amended, designates the Project site for undergraduate and graduate student housing.
Document Description
The proposed project would construct approximately 500 apartments and associated community facilities to accommodate undergraduate and graduate students. The approval covers Phase I of the project (approximately 500 apartments on 30 acres). The environmental document evaluates the anticipated ultimate project, which would be approximately 1,000 apartments (on 73 acres). Phase I of the project would consist of apartments and support facilities of varied elevations, not to exceed three stories in height, on approximately 30 acres in the East Campus area of the University of California, Irvine campus.

Contact Information

Name
John E. Zimmermann
Agency Name
University of California, Irvine
Contact Types
Lead/Public Agency

Location

Cities
Irvine
Counties
Orange
Cross Streets
Culver Drive and Campus Drive
Zip
92697
Total Acres
Approx. 73
Parcel #
Various
State Highways
SR 73/55
Waterways
Upper Newport Bay / San Diego Creek / San Joaquin Marsh
Township
6S
Range
9W
Section
89,90,
Base
52'30"
Other Location Info
University of California, Irvine
Other Information
Section cont: 99, 100 Base continued: 117

Notice of Determination

Approving Agency
Regents of the University of california
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print