High Desert Power Project

8 Documents in Project

Summary

SCH Number
2000079029
Lead Agency
California Energy Commission
Document Title
High Desert Power Project
Document Type
NOD - Notice of Determination
Received
Posted
7/12/2000
Document Description
The project is a 678 to 720 megawatt natural gas fired combined cycle electricity generating facility. Cooling water will be obtained from the State Water Project (SWP), and backup water supply will be provided from groundwater banking of SWP water. A new 7.2 mile 230 kilovolt transmission line will be built to interconnect the project to the Southern California Edison Company's Victor Substation. A 2.75 mile natural gas pipeline will be constructed by Southwest Gas Company to provide fuel for the project.

Contact Information

Name
Richard Buell
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency

Location

Cities
Victorville
Counties
San Bernardino

Notice of Determination

Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print