Murrieta Creek Phase II Project

9 Documents in Project

Summary

SCH Number
2000071051
Lead Agency
United States Army, Army Corps of Engineers (USACE)
Document Title
Murrieta Creek Phase II Project
Document Type
NOD - Notice of Determination
Received
Posted
1/22/2015
Present Land Use
Existing flood control channel
Document Description
CDFW is executing a Lake or Streambed Alteration Agreement (SAA # 1600-2012-0200-R6 [Revision 1]) pursuant to Section 1602 of the Fish and Game Code to the project Applicant Riverside County Flood Control and Water Conservation District, represented by Mr. Warren Williams, 1995 Market Street, City of Riverside, State of California, 92501, Phone (951) 955-1233. For the Murrieta Creek Phase II Project (Project), the Applicant is proposing the construction, operation, and maintenance of an approximately 13,000 linear foot section of Murrieta Creek generally between Winchester Road and 1st Street. Construction activities include channel excavation, construction of side slopes and erosion protection, grade stabilizing structures, drop inlets, maintenance roads, and access ramps. The Project also includes the ongoing operation and maintenance of the facilities following completion of the construction activities. Overall, the project will impact a total of 106.52 acres of streambed and associated habitat including permanent impacts to 9.58 acres, temporary impacts to 55.27 acres, and ongoing, annual impacts of 41.67 acres.

Contact Information

Name
Kimberly Freeburn-Marquez
Agency Name
CDFW Inland Deserts Region 6
Contact Types
Lead/Public Agency

Location

Cities
Murrieta, Temecula, Wildomar
Counties
Riverside
Cross Streets
Main Street and Old Town Front Street
Zip
92590
State Highways
Hwy 15, 79
Waterways
Murrieta Creek
Township
7-8S
Range
3W
Base
SBB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes