Elkhorn Boulevard Pipeline Project, 49AD

Summary

SCH Number
2000069020
Lead Agency
City of Sacramento
Document Title
Elkhorn Boulevard Pipeline Project, 49AD
Document Type
NOD - Notice of Determination
Received
Posted
6/23/2000
Document Description
Elkhorn Boulevard Pipeline Relocation Project - The project is part of the North Natomas Comprehensive Drainage Plan flood control improvements. Currently 380 acres of farmland, north of Elkhorn Boulevard and 7,000 feet west of the East Drainage Canal drains into the Reclamation District 1000 C-2 drain, which discharges into the East Drainage Canal, south of Del Paso Road. Three alternative drainage methods are proposed to move the discharge location of the agricultural drainage from the C-2 drain and transport the water to the East Drainage Canal. Alternative 1A would intercept drainage from the C-2 drain via an existing channel that would be widened (north of Elkhorn Blvd.), a channel that would be constructed (north of Elkhorn Blvd.), and then through a new pipeline (south of Elkhorn Blvd.) that would transport water to the East Drainage Canal. Alternative 1B would intercept drainage from the C-2 drain and transport water to the East drainage Canal via a channel that would be constructed south of Elkhorn Blvd to a new pipeline. Alternative 2 would intercept drainage water from the C-2 drain and transport it via a new pipeline south of Elkhorn Blvd. to the East Drainage Canal. The City's preferred alternative is Alternative 2.

Contact Information

Name
Bob Cooper / Colleen Laubinger
Agency Name
City of Sacramento, Nbrhds, Planning & Dev. Svcs. Dept.
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento

Notice of Determination

Approving Agency
City of Sacramento City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.