U.S. Widening Project From Bernal Rd. to Cochrame Rd. in Santa Clara County.

9 Documents in Project

Summary

SCH Number
2000062025
Lead Agency
California Department of Transportation, District 4
Document Title
U.S. Widening Project From Bernal Rd. to Cochrame Rd. in Santa Clara County.
Document Type
NOD - Notice of Determination
Received
Posted
8/16/2001
Document Description
The project consists of widening Highway 101 and included in that will be a bridge widening to accommodate the HOV ramp at the existing Coyote Creek crossing. The current low flow channel will be realigned in one location to protect one existing pier that is being exposed by scouring. Trees that may have blocked and redirected high flows toward the pier will be removed and the creekbed will be regraded to direct flows away from the pier. Rock slope protection will be placed below grade around existing exposed bents (piers) in the creekbed. The California Department of Fish and Game (DFG) is executing a Lake and Streambed Alteration Agreement Number R3-2001-0117 pursuant to section 1601 of the Fish and Game Code to the project operator, Jeff Funk/Santa Clara Valley Transportation Authority.

Contact Information

Name
Scott Wilson
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Morgan Hill, San Jose
Counties
Santa Clara
Cross Streets
Bernal Road to Cochrane Road
State Highways
U.S. 101, SR 85, 82
Railways
UPRR
Schools
Burnett(s)
Waterways
Coyote Creek

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.