U.S. Widening Project From Bernal Rd. to Cochrame Rd. in Santa Clara County.

9 Documents in Project

Summary

SCH Number
2000062025
Lead Agency
California Department of Transportation, District 4
Document Title
U.S. Widening Project From Bernal Rd. to Cochrame Rd. in Santa Clara County.
Document Type
NOD - Notice of Determination
Received
Posted
8/16/2001
Document Description
The project consists of widening Highway 101 and included in that will be a bridge widening to accommodate the HOV ramp at the existing Coyote Creek crossing. New bridges will be attached to existing bridges for both the northbound and southbound directions of the freeway, so that each will be three piers wide instead of two as currently exists. A total of four new piers will be constructed, all outside of tributary waters. Work will require removal of vegetation under bridges, construction of false work for pouring concrete bridges, excavation for the construction of bridge footings, and construction of bridge piers. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number R3-2001-0116 pursuant to section 1601 of the Fish and Game Code to the project operator, Jeff Funk/Santa Clara Valley Transportation Authority.

Contact Information

Name
Scott Wilson
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Morgan Hill, San Jose
Counties
Santa Clara
Cross Streets
Bernal Road to Cochrane Road
State Highways
U.S. 101, SR 85, 82
Railways
UPRR
Schools
Burnett(s)
Waterways
Coyote Creek

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No