Fairmont Avenue Extension

5 Documents in Project

Summary

SCH Number
2000041024
Lead Agency
California Department of Transportation, District 7
Document Title
Fairmont Avenue Extension
Document Type
NOD - Notice of Determination
Received
Posted
7/1/2008
Document Description
The project proposes to alter the streambed by improving and extending an existing street (Fairmont Avenue), from its current terminus at San Fernando Road to Flower Street. This extension includes elevating Fairmont Avenue, via a grade-separation viaduct, over San Fernando Road, over the Southern California Regional Rail Authority (SCRRA) railroad tracks and finally over the Verdugo Wash before coming back down to grade north of the Verdugo Wash. The improvements will provide congestion relief for regional and local traffic and improve safety along the affected roadways. There will be no traditional dredging activities associated with this project. The project will result in less than or equal to 0.01 acre of permanent impacts to streambed, bank, and channel. There will be roughly 0.93 acre of temporary impacts from placement of temporary flow diversion facilities (cofferdams, sandbags or similar material) and mobilization of construction staff and equipment.

Contact Information

Name
Jamie Jackson
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Glendale, Glendale, Los Angeles, City of, Los Angeles
Counties
Los Angeles
Cross Streets
State Route 134/San Fernando Road
Zip
91203
State Highways
State Route 134/and Interstate 5
Railways
SCRRA
Schools
Columbus Elementary, E.J. Toll Middle School, Herbert Hoover H.S
Waterways
Los Angeles River, Verdugo Wash

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No