Hollister Air Attack Base Relocation Project

2 Documents in Project

Summary

SCH Number
2000031071
Lead Agency
California Department of Forestry and Fire Protection (CAL FIRE)
Document Title
Hollister Air Attack Base Relocation Project
Document Type
NOD - Notice of Determination
Received
Posted
6/15/2000
Document Description
The project consists of the acquisition and construction of a 5,280 square foot office building with a dispatch/observation tower, a 2,040 square foot airbase shop and 4-bay garage, a 400 square foot generator building, a 400 square foot aircraft mechanic shop and a 6,000 square foot automotive maintenance shop and bulldozer/transport building. Other new facility features are paving, air tanker loading pad, aircraft areas, retardant mixing systems, and security controls. Site work includes grading, drainage, and compacting the soil, cutting trenches, laying electrical conduits, and installing telephone lines, cable television, water, sewer systems and gas lines. The existing facility will be demolished and removed from the site. The proposed project is necessary because the existing CDF Hollister Air Attack Base Facility no longer meets safety and operational needs.

Contact Information

Name
Fred Lambert
Agency Name
California Department of Forestry
Contact Types
Lead/Public Agency

Location

Cities
Hollister
Counties
San Benito
Total Acres
12
State Highways
156
Airports
Hollister
Other Location Info
State Route 156 / Finn Road / Aerostar

Notice of Determination

Approving Agency
California Department of Forestry and Fire Protection
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.