Guadalupe River Flood Control Project, from I-880 to I-280

10 Documents in Project

Summary

SCH Number
1999102056
Lead Agency
Santa Clara Valley Water District
Document Title
Guadalupe River Flood Control Project, from I-880 to I-280
Document Type
NOD - Notice of Determination
Received
Posted
7/1/2008
Document Description
As part of the greater flood control project, this portion consists of the construction of a 12-foot wide lower west bank riverwalk/maintenance road beneath Coleman Avenue Bridge, construction of a 12-foot wide east bank maintenance access ramp at Coleman Avenue Bridge, and modifications to the existing Coleman Avenue Bridge abutments. The project is located on the Guadalupe River beneath Coleman Avenue in San Jose. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement number 1600-2008-0187-3 pursuant to Section 1602 of the Fish and Game Code to the project applicant, Ryan Heacock, Santa Clara Valley Water District.

Contact Information

Name
Tami Schane
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
West Santa Clara and Guadalupe Parkway
Zip
95118
Total Acres
41.12
Parcel #
259-24-025; 259-23-019
State Highways
87-, I-280, I-880
Railways
UPRR
Airports
San Jose International
Schools
San Jose State University
Waterways
Guadalupe River, San Francisco Bay, Los Gatos Creek
Township
7S
Range
1E
Base
MDB&M

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.