State Route 4/Loveridge Road Flood Relief Project
4 Documents in Project
Summary
SCH Number
1999102007
Lead Agency
City of Pittsburg
Document Title
State Route 4/Loveridge Road Flood Relief Project
Document Type
NOD - Notice of Determination
Received
Posted
12/28/2001
Document Description
The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number R3-2000-1330 pursuant to Section 1601 of the Fish and Game Code to the project operator, Nasser Shirazi/ City of Pittsburg. The applicant proposes to alleviate flooding of State Route 4 at Loveridge Road in Pittsburg, Contra Costa County, the Operator proposes to construct "channel improvements" to Kirker Creek north of California Avenue downstream to 170 feet east of Loveridge Road. The project is broken into 3 segments: approximately 820 linear feet of Kirker Creek will become a concrete lined channel with a bed width of 20' and 2:1 slopes, approximately 620 feet of existing 84" culvert will be removed and an earthen channel will be created, the existing box culverts on the north side of the Pittsburg/Antioch Highway will be extended by approximately 25 feet downstream (north) and will discharge into Kirker Creek using wingwalls and loose rock riprap.
Contact Information
Name
Greg Martinelli
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Pittsburg
Counties
Contra Costa
Cross Streets
California Avenue, Loveridge Road, Pittsburg - Antioch Highway
State Highways
SR-4
Railways
UPRR, BNSF RR
Schools
Martin Luther King Jr.
Waterways
San Joaquin River, Kirker Creek, Dowest Slough
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.