San Vicente Wastewater Treatment Plant Expansion

4 Documents in Project

Summary

SCH Number
1999101015
Lead Agency
Ramona Municipal Water District
Document Title
San Vicente Wastewater Treatment Plant Expansion
Document Type
NOD - Notice of Determination
Received
Posted
11/24/1999
Present Land Use
General Plan Designations: Public/Semi-Public (22) Zoning: A--70 (limited ag) Present land use is existing wastewater treatment plant including plant facility.
Document Description
Expansion of the existing San Vicente Wastewater Treatment Plant to increase the average dry weather flow capacity from 0.60 million gallons per day (mgd) to 0.80 mgd. The proposed expansion includes the following three major components: 1.) improvements and additions to the treatment process facilitries at the reclamation plant site; 2.) construction of a new, 93 acre-foot storage pond and stream diversion channel on-site, west of the existing storage ponds; and, 3.) construction of a reclaimed water line from the new storage pond and under San Vicente Road to the San Vicente Golf Course, located approximately 1.5 miles to the east of the site.

Contact Information

Name
Robert A. McCullough
Agency Name
Ramona Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Ramona
Counties
San Diego
Cross Streets
San Vicente Rd./ Wildcat Canyon Rd
Total Acres
10
Parcel #
258-100-07,08,09 & 10
State Highways
78 & 76
Waterways
San Vicente Creek
Township
13S
Range
1E
Section
36

Notice of Determination

Approving Agency
Ramona Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print