Lower Clear Creek Floodway Rehabilitation Project

6 Documents in Project

Summary

SCH Number
1999092102
Lead Agency
Western Shasta Resource Conservation District
Document Title
Lower Clear Creek Floodway Rehabilitation Project
Document Type
NOD - Notice of Determination
Received
Posted
7/20/2001
Document Description
The subject project would complete stream channel and floodplain rehabilitation efforts in a 1.6 mile section of lower Clear Creek that has been severely degraded by gravel extraction activities. The project will improve salmonid habitat by filling old mining pits with gravel, reconstructing functional floodplains, restoring a properly sized stream channel that is in balance with future flow and sediment supply conditions, and restoring native woody riparian vegetation. Gravel and cobble necessary for rehabilitation efforts would be obtained from dredger tailings that are available within the lower Clear Creek watershed. Two borrow sites have been indentified for restoration actions and would provide a source of borrow material for rehabilitation actions at the project site. A third site provides wetland creation opportunities in an area previously degraded by mining activities. Floodplain restoration and off channel wetlands would be created, where appropriate, at each borrow site during removal of dredger tailing piles.

Contact Information

Name
Mr. Jeff Souza, Projects Manager
Agency Name
Western Shasta Resource Conservation District
Contact Types
Lead/Public Agency

Location

Cities
Redding
Counties
Shasta
Township
31N
Range
6W
Section
32,34,
Base
MDB&M

Notice of Determination

Approving Agency
Western Shasta Resource Conservation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print