Coordinated Use Agreement for Conveyance Facilities and State Water Project Water Supplies Between San Bernadino Valley Municipal Water District and Metropolita

8 Documents in Project

Summary

SCH Number
1999091073
Lead Agency
San Bernardino Valley Municipal Water District
Document Title
Coordinated Use Agreement for Conveyance Facilities and State Water Project Water Supplies Between San Bernadino Valley Municipal Water District and Metropolita
Document Type
NOD - Notice of Determination
Received
Posted
4/18/2001
Document Description
Under this agreement, Metropolitan would purchase a portion of Valley District's SWP water supplies and Valley District would deliver the purchased supplies to Metropolitan's service area through the coordinated use of facilities and interconnections within the water conveyance systems of the two districts.

Contact Information

Name
Bob Reiter
Agency Name
San Bernardino Valley Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Colton, Highland, Loma Linda, Redlands, Rialto, San Bernardino, San Bernardino, Rialto, Colton, Loma Linda, Redlands, ..., Yucaipa
Counties
San Bernardino
State Highways
66, 38, 215 (30)
Railways
SPRR, BNSF
Airports
Redlands, Rialto Municipal
Waterways
Santa Ana River & Mill, Lytle, Cajon, Warm, City, and Plundge Creeks
Township
1&2N,
Range
1-4W
Other Information
cont. T1S, T2S cont. Airport San Bernardino International

Notice of Determination

Approving Agency
Board of Directors of the Metropolitan Water District
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print