Regional Water Facilities Master Plan

8 Documents in Project

Summary

SCH Number
1999091073
Lead Agency
San Bernardino Valley Municipal Water District
Document Title
Regional Water Facilities Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
2/21/2001
Document Description
The proposed project is construction and operation of facilities and programs associated with the San Bernardino Valley Municipal Water District Regional Water Facilities Master Plan. Proposed improvements would be constructed over an indefinite period of time and include approximately 139,000 feet of pipelines ranging in size from 16 to 96 inches in diameter, nine pump stations with capacities of 10 to 100 cfs, three reservoirs ranging in size from 5 million to 100 million gallons, and an implementation of a groundwater management program as represented in the Draft and Final EIRs prepared for the project.

Contact Information

Name
G. Louis Fletcher
Agency Name
San Bernardino Valley Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Colton, Highland, Loma Linda, Redlands, Rialto, San Bernardino, San Bernardino, Rialto, Colton, Loma Linda, Redlands, ..., Yucaipa
Counties
San Bernardino
State Highways
66, 38, 215 (30)
Railways
SPRR, BNSF
Airports
Redlands, Rialto Municipal
Waterways
Santa Ana River & Mill, Lytle, Cajon, Warm, City, and Plundge Creeks
Township
1&2N,
Range
1-4W
Other Information
cont. T1S, T2S cont. Airport San Bernardino International

Notice of Determination

Approving Agency
San Bernardino Valley Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.