Maariposa County Landfill Permit Revision
4 Documents in Project
Summary
SCH Number
1999091057
Lead Agency
Mariposa County
Document Title
Maariposa County Landfill Permit Revision
Document Type
NOD - Notice of Determination
Received
Posted
3/27/2015
Present Land Use
N/A - Conforms to Existing Land Uses, Zoning, and General Plan Designations.
Document Description
For the current Mariposa County Solid Waste Facility Permit, SWIS No. 22-AA-0001 (issued on February 29, 2000 pursuant to an adopted Negative Declaration), the Mariposa County Board of Supervisors, on March 24, 2015, approved an Agreement regarding the Disposal and Use of Material from the Ferguson Project for landfill daily cover material. The Mariposa County Board of Supervisors adopted findings pursuant to Public Resources Code Section 21166 and Guidelines Section 15162, determining that no subsequent environmental review was required to approve the above referenced agreement regarding importation and processing of soil cover material. The below numbered determinations describe the CEQA compliance conducted as part of the Local Enforcement Agency's (Mariposa County Health Department's) issuance of the Solid Waste Facility Permit, SWIS No. 22-44-0001 on February 29, 2000. The below numbered determinations also describes the CEQA compliance considered as part of the California Integrated Waste Management Board's (CIWMB) concurrence of the Solid Waste Facility Permit on February 25, 2000. The Notice of Determination filed as part of the permit issuance (approval) is attached and incorporated by this reference.
Contact Information
Name
Sarah Williams
Agency Name
Mariposa County Board of Supervisors
Contact Types
Lead/Public Agency
Phone
Location
Cities
Mariposa
Counties
Mariposa
Total Acres
931.200
State Highways
160, 49, 120, 140
Notice of Determination
Approving Agency
Mariposa County Local Enforcement Agency
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.