Guadalupe River Outfall Upgrade

4 Documents in Project

Summary

SCH Number
1999082004
Lead Agency
City of San Jose
Document Title
Guadalupe River Outfall Upgrade
Document Type
NOD - Notice of Determination
Received
Posted
6/26/2001
Document Description
The project is the replacement of an existing 36-inch tall outfall with a 48-inch outfall in Guadalupe River in the City of San Jose. The replacement will occur at the existing outfall location at the edge of the wide flood controlled channel of Guadalupe River. The project involves the removal of the existing 36-inch outfall structure and associated grouted rip rap and replacement with a 48-inch outfall. A backhoe and other minor equipment will be utilized on the site. The project will take about one week to complete. The rip rap around the new outfall structure will be grouted with concrete. The California Department of Fish and Game (CDFG) is executing a Lake and Streambed Alteration Agreement number R3-2000-1434 pursuant to Section 1603 of the Fish and Game Code to the project operator, Tom Jodry / Legacy Partners.

Contact Information

Name
Scott Wilson
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
State Route 237/Great America PKWY./Gold St./San Tomas Aquino Creek
Total Acres
70.5
Parcel #
015-34-016, 047, 059, 067, 068, 070; 015-35-030, 031; 104-01-033, 047, 048
State Highways
SR 237
Railways
UPRR /SPRR
Schools
Santa Clara Unified
Waterways
Guadalupe River, San Tomas, Aquino Creek

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print