Addendum to the Final Program Environmental Impact Report for the City of Davis General Plan Update and Project EIR for Establishment of a New Junior High Schoo

2 Documents in Project

Summary

SCH Number
1999072014
Lead Agency
Davis Joint Union School District (DJUSD)
Document Title
Addendum to the Final Program Environmental Impact Report for the City of Davis General Plan Update and Project EIR for Establishment of a New Junior High Schoo
Document Type
NOD - Notice of Determination
Received
Posted
11/10/2008
Document Description
The Addendum was prepared for the implementation of recommendations from the General Plan Update Steering Committee on processing applications for possible residential development in the Cit. of Davis and minor amendments to the Cit. of Davis general plan text. The proposed project includes: 1. An approach to processing residential development through 2010; 2. A list of sites that would be processed upon application for entitlements, all of which would be subject to discretionary review; 3. Continued processing of other sites that would not provide units before 2010 and would be subject to discretionary review and environmental impact reports; 4. Amendments to the GP text that would delete the limit of 64,000 population in 2010 and remove the requirement for growth management allocation for infill developments; and 5. General policy language on mix of residential units. Modifications of the Steering Committee recommendations are also addressed in the Addendum.

Contact Information

Name
Robert Wolcott
Agency Name
City of Davis
Contact Types
Lead/Public Agency

Location

Cities
Davis
Counties
Yolo
Cross Streets
Mace and Covell Boulevard
Total Acres
90
Parcel #
71-130-04
State Highways
I-80
Railways
Union Pacific
Waterways
Putah Creek, Yolo Bypass, Covell Drain

Notice of Determination

Approving Agency
City of Davis
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print