Dyer Lane, Easement Sewer, and Pump Station Project

59 Documents in Project

Summary

SCH Number
1999062020
Lead Agency
Placer County
Document Title
Dyer Lane, Easement Sewer, and Pump Station Project
Document Type
NOD - Notice of Determination
Received
Posted
12/24/2021
Document Description
The proposed Project includes roadway improvements, a force main sewer line, a gravity sewer line, and a sewer pump station. Approximately 1,430 linear feet of sewer line will be installed via trenching. The sewer line will be composed of pipe that varies from 18 inches to 24 inches in width. A sewer lift station, which will accept gravity flow from a 30-inch sewer collector and lift it to be distributed eastward by the sewer force main, will also be constructed. Approximately 15,200 linear feet of a sewer force main will be installed to extend from the west end of the Project site to the east end of the Project site. The sewer force main will be installed via trenching and will be composed of a 12-inch pipe. A 14-foot-wide gravel maintenance road will be built to allow access to the sewer line.

Contact Information

Name
Lynn Coster
Agency Name
Central Valley Regional Water Quality Control Board
Job Title
Senior Environmental Scientist
Contact Types
Responsible Agency

Location

Cities
Roseville
Counties
Placer
Regions
Northern California
Township
10 N
Range
5 E
Section
9-12
Base
MDB&M

Notice of Determination

Approving Agency
Central Valley Regional Water Quality Control Board
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Placer
Final Environmental Document Available at
The final EIR with comments and responses is available to the general public at: County of Placer - Placer Vineyards Specific Plan - Environmental Impact Report (https://www.placer.ca.gov/3566/Environmental-Impact-Report).

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.