Phase II of the Riverview at Santee Project - TCSPA 04-01 (SAA #1600-2008-0042-R5)

11 Documents in Project

Summary

SCH Number
1999031096
Lead Agency
City of Santee
Document Title
Phase II of the Riverview at Santee Project - TCSPA 04-01 (SAA #1600-2008-0042-R5)
Document Type
NOD - Notice of Determination
Received
Posted
9/10/2008
Present Land Use
Stockpil area, vacant agricultural land, women's detention facility, and hospital. Z: Town Center GP: Town Center Specific Plan
Document Description
CDFG is intending to execute a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code (SAA #1600-2008-0042-R5) to the project applicant, Jesse Luevano of Ryan Companies US, Inc. The applicant proposes to alter the stream to construct Phase II of the Riverview at Santee Project. Project activities include relocation and construction of the Las Colinas drainage channel to convey storm water from the project and surrounding area. The channel wold be an earthen channel approximately 60 feet wide at the channel bottom.

Contact Information

Name
Kelly Fisher
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Santee
Counties
San Diego
Cross Streets
Mission Gorge Road / Magnolia Avenue
Total Acres
154
Parcel #
381-050-51, 37; 381-161-29
State Highways
67
Airports
Gillespie Field
Schools
Cajon Park and Santana HS
Waterways
San Diego River
Township
15S
Range
1W
Base
El Cajon

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print