Lower Mission Creek Flood Control Project

9 Documents in Project

Summary

SCH Number
1998101061
Lead Agency
Santa Barbara, City of (City of Santa Barbara)
Document Title
Lower Mission Creek Flood Control Project
Document Type
NOD - Notice of Determination
Received

Document Description
Approve, adopt, and authorize a Resolution of Necessity for the acquisition of the fee interest in the real property for Reach 2B-Phase II and Reach 3 - the Lower Mission Creek project. The Lower Mission Creek Flood Control project is a federal U.S. Army Corps of Engineer project that has been under the study and development since the 1960's. The Corps completed a feasibility study in 2000. The County and City of Santa Barbara are construction the project in sections (reaches) as funding becomes available. As locally funded project, the Santa Barbara County Flood Control and Water Conservation is responsible for the right of way acquisition associated with the Lower Mission Creek Flood Control project. After environmental review was completed, staff considered acquiring only permanent and temporary easements from the property; however upon review of the entire Mission Creek Project, it has become apparent that the property provides a strategic location that is beneficial for the current and future construction, access, staging, and operation and maintenance of the overall Mission Creek project.

Contact Information
Maureen Spencer
Santa Barbara County Flood Control and Water Conservation
130 E. Victoria St, Suite 200
Santa Barabara, CA 93101

805-568-3437

Location

Cities
Santa Barbara
Counties
Santa Barbara
Cross Streets
Between Carrillo St. and the Ocean
Zip
93101
Total Acres
N/A
Parcel #
Several Dozen
State Highways
US 101, SR 225, SR 192-SR 144
Railways
UPRR
Schools
Santa Barbara City College
Waterways
Mission Creek, Laguna Channel

Notice of Determination

Approving Agency
Santa Barbara County Flood Control and Water Conservation
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
130 E. Victoria St, Suite 200, Santa Barbara, CA 93101

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search