San Andreas Reservoir Road Improvement Project (Lake Alteration Agreement No. EPIMS-SMO-40265-R3)

16 Documents in Project

Summary

SCH Number
1998082030
Lead Agency
City and County of San Francisco
Document Title
San Andreas Reservoir Road Improvement Project (Lake Alteration Agreement No. EPIMS-SMO-40265-R3)
Document Type
NOD - Notice of Determination
Received
Posted
6/26/2024
Document Description
This project will provide road improvements along the perimeter of San Andreas Reservoir in order to maintain access to water utility infrastructure, and protect infrastructure from reservoir debris. Project activities include grading and backfilling to reconstruct slopes of the reservoir's eastern shoreline, riprap installations, installation of a soldier-pile wall, replacement of a debris boom anchor, and replacement of two corrugated metal culverts.

Contact Information

Name
Serge Glushkoff
Agency Name
CDFW
Job Title
Environmental Scientist
Contact Types
Responsible Agency

Location

Cities
San Mateo
Counties
San Mateo
Regions
San Francisco Bay Area
Other Location Info
The project is located on San Andreas Reservoir in the unincorporated portion of the County of San Mateo, State of California; work will occur at four areas along the San Andreas Reservoir shoreline: Latitude 37.602330, N, Longitude - 122.427916; 37.603874, N, Longitude -122.429375; 37.606128, N, Longitude -122.43204; 37.581727, N, Longitude -122.410421; and 37.580250, N, Longitude -122.413563.

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
County Clerks
San Francisco, San Mateo
Final Environmental Document Available at
CDFW’s region 3 office.

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print