City College of San Francisco Chinatown/North Beach Campus
6 Documents in Project
Summary
SCH Number
1998031039
Lead Agency
San Francisco Community College District
Document Title
City College of San Francisco Chinatown/North Beach Campus
Document Type
NOD - Notice of Determination
Received
Posted
10/25/2007
Present Land Use
The project site currently includes a surface parking lot. The project site is located in the Chinatown Business District (CCB) zoning district, and the 65-A Height and Bulk District. The project site is within the Chinatown Area Plan in the City of San Francisco General Plan.
Document Description
The authorized project involves construction of a 185-foot to 192-foot tall, 14-story building on Lots 9 and 10 and a 65-foot tall, four-story building on Lot 5. The building on Lots 9 and 10 shall contain approximately 78,894 of assignable square feet as defined by the State. The building on Lot 5 shall contain approximately 14,890 of assignable square feet as defined by the State. No parking will be provided on-site.
Contact Information
Name
Peter Goldstein
Agency Name
San Francisco Community College District
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Francisco
Counties
San Francisco
Cross Streets
Washington Street / Kearney Street
Total Acres
0.29 (12,611 sf)
Parcel #
Block 195, Lots 9, 10
State Highways
I-80, I-280
Waterways
San Francisco Bay
Township
2S
Range
5W
Section
33
Base
SF North
Notice of Determination
Approving Agency
San Francisco Community College District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.