Construction and Management of an Artificial Reef in the Pacific Ocean near San Clemente, California: Wheeler North Reef Expansion Project

8 Documents in Project

Summary

SCH Number
1998031027
Lead Agency
California State Lands Commission
Document Title
Construction and Management of an Artificial Reef in the Pacific Ocean near San Clemente, California: Wheeler North Reef Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
2/4/2019
Present Land Use
none - Open ocean
Document Description
Southern California Edison has applied to the CA State Lands Commission to amend Lease No. PRC 8097 to expand the Wheeler North Reef. Construction, long-term monitoring, and evaluation of the Wheeler North Reef is required under a Coastal Development Permit issued by the CA State Lands Commission for the operation of San Onofre Nuclear Generating Station Units 2 and 3. To ensure that Wheeler North Reef will meet all absolute and relative performance standards under the CCC's CDP, the proposed project would supplement the existing Wheeler North Reef by creating approx 210 acres of additional kelp reef on low-relief quarry rocks. The State Lands Commission action is an amendment of a 37-year General Lease - Non-Income Producing Use through August 1, 2035.

Contact Information

Name
Cheryl Hudson
Agency Name
State Lands Commission
Contact Types
Lead/Public Agency

Location

Cities
San Clemente
Counties
Orange
Cross Streets
none - offshore
Total Acres
210
State Highways
1
Waterways
Pacific Ocean

Notice of Determination

Approving Agency
CA State Lands Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.