CITY OF LODI WHITE SLOUGH POLLUTION CONTROL FACILITY EXPAN.

2 Documents in Project

Summary

SCH Number
1998022026
Lead Agency
City of Lodi
Document Title
CITY OF LODI WHITE SLOUGH POLLUTION CONTROL FACILITY EXPAN.
Document Type
NOD - Notice of Determination
Received
Posted
7/7/2003
Document Description
Proposed interim aeration filtration, and UV disinfection improvements would be constructed within the main site described as: 1) Installing new multi-stage centrifugal blowers in the existing blower room; 2) Improving the blower building power supply to accommodate the new blowers; 3) Replacing of the aeration diffusers in two existing aeration basins; 4) Relocating the pumping station that supplies water to the NCPA power plant; 5) Removing and either disposing of or relocating sludge from an existing pond (i.e., the Aerated Pond) that would be used to equalize irrigation flowers; 6) Installing a pumping station to lift secondary clarifier effluent to the filters; 7) Installing granular or cloth-media tertiary filters; 8) Installing a coagulant feed equipment and building; 9) Installing clearwell and backwash pumping facilities; 10) Filling a portion of an existing pond (i.e., the Equalization Pond) to create a site for improvements (i.e., pumping station, tertiary filters, coagulant feed equipment and building, clearwell and backwash pumping facilities, and ultraviolet disinfection facilities); and 11) Installing ultraviolet disinfection facilities over the infilled pond area.

Contact Information

Name
J.D. Hightower
Agency Name
City of Lodi
Contact Types
Lead/Public Agency

Location

Cities
Lodi
Counties
San Joaquin
Cross Streets
I-5/Eight Mile Road
Parcel #
055-120-05
State Highways
I-5
Waterways
Delta

Notice of Determination

Approving Agency
City of Lodi, Community Development Department
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print