LAX Master Plan

15 Documents in Project

Summary

SCH Number
1997061047
Lead Agency
Los Angeles World Airports (LAWA)
Document Title
LAX Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
12/22/2004
Present Land Use
M2 (Q) and M3
Document Description
The Los Angeles International Airport Master Plan Program represents a long-term vision of the airport's facilities and will serve as a strategic plan to guide future development. At its meeting on December 14, 2004, the City Council, of the City of Los Angeles considered the LAX Master Plan Program and reports the following actions taken as follows: 1. Adopted the resolution to overrule the Los Angeles County Airport Land Use Commission determination regarding the LAX Master Plan Actions based on the proposed State Aeronautics Act; complied with CEQA by certifying the EIR, adoptin the Findings, Statement of Overriding Considerations and the Mitigation Monitoring & Reporting Program; and approved the LAX Master Plan Program. 2. Adopted the ordinances amending the Los Angeles Municipal Code to provide for the LAX Master Plan Program. 3. Adopted the ordinance establishing the LAX Specific Plan.

Contact Information

Name
Herb Glasgow
Agency Name
City of Los Angeles Department of Airports
Contact Types
Lead/Public Agency

Location

Cities
Inglewood, Los Angeles, Los Angeles, City of
Counties
Los Angeles
Cross Streets
Imperial and Sepulveda
Total Acres
+/-3500
State Highways
I-405/I-105
Railways
MTA Green Line and BNSF
Airports
LAX & Hawthorne Municipal
Waterways
Pacific Ocean

Notice of Determination

Approving Agency
City of Los Angeles City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print