Airport-Larkfield-Wikiup Sanitation Zone - Storage, Reclamation, and Treatment Facilities Project
5 Documents in Project
Summary
SCH Number
1997042057
Lead Agency
Sonoma County
Document Title
Airport-Larkfield-Wikiup Sanitation Zone - Storage, Reclamation, and Treatment Facilities Project
Document Type
NOD - Notice of Determination
Received
Posted
12/8/1999
Document Description
The Airport - Larkfield - Wikiup Sanitation Zone (ASZ), which is owned and operated by the Sonoma County Water Agency (Agency), provides wastewater service to approximately 2,400 parcels in the unincorporated areas of Airport, Larkfield, and Wikiup. The Agency's Board of Directors approved the Preferred Project described in the Final Environmental Impact Report for the project. Please refer to figure 1 for the locations of the project components. The preferred project consists of the phased construction of the following project components:
Construct up to 110 million gallons of storage on Site D
Use Pipeline Route No. 4 to connect existing and future facilities to Site D
Construct up to 70 million gallons of storage on Site C
Use Site C for disposal (reclamation) until this site is used for storage
Use Pipeline Route No. 7 to connect existing and future facilities to Site C
Upgrade the ASZ treatment plant to a tertiary level
Discharge into the City of Santa Rosa's Geysers Recharge project
Use Pipeline Route No. 3 to connect to pipeline for Geyer's Recharge project
Pursue additional disposal areas as available and study alternative disposal methods
Contact Information
Name
DAVID CUNEO
Agency Name
SONOMA COUNTY WATER AGENCY
Contact Types
Lead/Public Agency
Phone
Location
Cities
Windsor
Counties
Sonoma
Cross Streets
Mark West Station Road and Slusser Road, Windsor Road and Sander
State Highways
101
Railways
NWP Railroad
Airports
Sonoma County
Waterways
Windsor & Airport Creeks
Township
8N
Range
8-9W
Section
19,25,
Base
Healdsbu
Notice of Determination
Approving Agency
N/A
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.