66KV SUBSTATION PROJECT

Summary

SCH Number
1996104814
Lead Agency
Regents of the University of California
Document Title
66KV SUBSTATION PROJECT
Document Type
NOD - Notice of Determination
Received
Posted
9/12/1996

Document Description

Contact Information
AERYN RICHMONDE
UNIVERSITY OF CALIFORNIA, SANTA BARBARA
Lead/Public Agency
BUDGET & PLANNING
SANTA BARBARA, CA 93106-2030

Phone : (805) 893-4746

Location

Cities
UC SANTA BARBARA
Counties
Santa Barbara

Notice of Determination

Approving Agency
N/A
Final Environmental Document Available at
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.